10.18. Comments with respect to the new model
There are two ways of looking at this case study with respect to the new model. The first would be to describe how it differs from the traditional model. The most visible differences were the absence of the following:
A standard client–vendor relationship with its contractual obligations and sign-offs (replaced by a partnership working towards mutually agreed objectives);
A detailed business case as a pre-requisite for starting the project (replaced by a feasibility study to determine what the best solution would be, with the business case only defined afterwards based on the outcome of the study);
IT–user interviews resulting in a detailed SoR (replaced by a three-day workshop session resulting in a 30-page document containing business definitions, process and data models);
The absence of a traditional project manager (replaced by an iterative project manager who, in addition to managing tasks and deliverables, also had to play a creative role in proposing a workable solution and ensuring the buy-in of the project team);
Sequential teams of analysts, developers and testers working to the waterfall method (replaced by people with the combined role of analyst/developer, using iterative methods in conjunction with business users);
'Corrective maintenance' within the first few months to fix serious design and usability issues (replaced by minor ongoing releases to fix bugs and incorporate usability suggestions from the call-centre agents). ...