Project Scoping 19
Facilities management
IT management
Management of the business units that use the network
The Project Overview Statement will be accompanied by a cover letter
asking the recipients to review the document and indicate their agreement to
and understanding of the contents. In general, it is prudent to allow five
business days for a response; and in some organizations, the cover letter can
include words to the effect that a lack of response indicates agreement. While
the aim here is not to deny anyone the opportunity to respond, we cannot
allow the project to be held up because of a simple failure to respond.
If responses are received that indicate a lack of agreement or understanding
of the contents of the Project Overview Statement, ...