wait for those five days to elapse before starting the preparation work for the
project itself.
Project Scope Change
It is inevitable that, after the Project Overview Statement (Exhibit 9) has been
approved and the Project Scope Document (Exhibit 10) drafted, someone will
require a change in the scope of the project. The key to a successful project
is to effectively manage scope change.
Managing scope change begins with a formal process for requesting a
change in scope. Exhibit 11 provides a sample Scope Change Request Form.
The project manager should be the first to review requests for scope change
and should be the “gatekeeper” (i.e., ...
Become an O’Reilly member and get unlimited access to this title plus top books and audiobooks from O’Reilly and nearly 200 top publishers, thousands of courses curated by job role, 150+ live events each month, and much more.
O’Reilly covers everything we've got, with content to help us build a world-class technology community, upgrade the capabilities and competencies of our teams, and improve overall team performance as well as their engagement.
Julian F.
Head of Cybersecurity
I wanted to learn C and C++, but it didn't click for me until I picked up an O'Reilly book. When I went on the O’Reilly platform, I was astonished to find all the books there, plus live events and sandboxes so you could play around with the technology.
Addison B.
Field Engineer
I’ve been on the O’Reilly platform for more than eight years. I use a couple of learning platforms, but I'm on O'Reilly more than anybody else. When you're there, you start learning. I'm never disappointed.
Amir M.
Data Platform Tech Lead
I'm always learning. So when I got on to O'Reilly, I was like a kid in a candy store. There are playlists. There are answers. There's on-demand training. It's worth its weight in gold, in terms of what it allows me to do.