FAST TRACK TOP TEN
75
the risk owner to communicate with the assumption originator
(if the risk owner did not originate the assumption) to make sure
that they fully understand the risk and underlying drivers. The
risk owner should also consider what actions will be required
and who would be the best person to undertake those actions
(i.e. the risk action manager). For ongoing risks the risk owner
will need to get an update on the risk plan status from the risk
action man
ager.
During the risk review board: discuss the risks in priority
order as indicated by the bubble diagram (i.e. those nearest to
the origin first). The process for ...