64 ◾ Software Testing as a Service
4.6 Schedule versus Effort
In the waterfall model, each subprocess in software development strictly follows the
preceding subprocess. e subsequent subprocess always starts after the preceding
subprocess ends. at is why we tackle the design phase after the requirements phase
has been completed, the coding phase after the design phase has been completed,
and so on. So, in the waterfall model, the schedule is always equal to the effort for
the project. Accordingly the software test processes also follow the strict regime that
is followed by the development and design processes (see Figure 4.2).
In agile develop ...