94 • Project Planning and Project Success: e 25% Solution
TABLE15.5
Multiple Regression of Final Model against Success Measure
with Moderator Interaction Terms
Regression Summary for Dependent Variable:
Success Measure
R = .387 Adjusted R² = .145 p < .0001
B p-Level
Intercept 3.222 0.000
Planning eort index 12.648 0.000
Planning eort index
2
–24.405 0.000
WBS Planning eort index –2.924 0.000
WBS Planning eort index
2
4.653 0.000
Experience Planning eort index –3.960 0.000
Experience Planning eort index
2
8.928 0.000
Internal Planning eort index 0.713 0.000
Internal Planning eort index
2
–1.495 0.005
TABLE15.4
MHRA Analysis for Team Size as Moderator in ...