10 2 • Construction Program Management
• Fire protection and Fire prevention (Fire extinguishers and
training)
• Housekeeping requirements (removal of debris)
• Field Sanitation – Toilets, supplier of potable water
• For Steel Erection – (there must be a separate site safety plan):
• Identies order of erection
• Laydown and staging areas
• Site roadways
• Plan to prevent elevated loads above other activities
• A steel erection Contractor shall not erect steel unless it has
received written notication that the concrete in the footings,
piers and walls or the mortar in the masonry piers and walls has
attained, on the basis of an appropriate ASTM [39] standard test
method of eld cured samples, either 75% of the intended mini-
mum compressive ...