Execution Process • 137
we resource-leveled the schedule to limit the peak usage of crawler cranes
from ve to four.
is technique can be used in a similar fashion for any resource that is
required on the project or program. Some examples are the following:
• e peak requirement for carpenters on a program. We used this
information to help negotiate a PLA agreement.
• e total amount of concrete required for a project. We used that
information to ensure availability and negotiate a better price.
• e amount of structural steel delivered to a project in a given week.
We used that information to coordinate the deliveries with local
trac oc ...