Chapter 7. Planning your workload 429
AWSJPL715I During the creation of a production plan, the planner has successfully
updated the preproduction plan.
.
.
.
AWSJPL504I The "planner" process has unlocked the database.
AWSJCL062I The production plan (Symnew) has been successfully extended.
Production days that are shorter than the default 24 hours use planman in the
same manner, but with different arguments passed to it than in the previous
examples. If the production plan is 6 hours long, you might see the -for flag option
passed to planman with the argument 0600, or the flag options -from and -to
passed with arguments that explicitly specify the ...