By default, you can only have one active sprint at one time. However, sometimes you may have multiple teams working on the same project, but in unrelated areas. In these cases, you may want to have multiple sprints running for the project, one for each team. You can enable parallel sprints using the following method:
Once this option is enabled, you will be able to start multiple sprints in the same project. Note that this is a global option, so all projects ...