Many work center operations will have time required for setup and teardown outside of the time consumed by actual production. This is certainly true for our T-shirt printing example. It takes time for someone to prepare a printing press with inks before the first T-shirt can be printed. For our example, we have estimated five minutes of setup time. Likewise, when we are done producing the last product in our work order, it takes time to clean up before setting up the next job. In this example, we have estimated another five minutes of time at the end of production for the Time after prod. operations.