ADDENDUM BMOC EXAMPLE 2
Beta Company Form 1812
Issue Date June 1, 2008
Effective June 8, 2008
BETA COMPANY
Field Work Review and Hazard Analysis
All work done by our field crews involves change, whether for new system installations or modifications of existing systems. To assure that assignments are carried out efficiently and that our crew members are not in situations where the risks are unacceptable, the crew supervisor shall complete Form 1812 prior to the start of an assignment to assure adequate planning.
As the supervisor considers the work to be done, a discussion/briefing will be held with crew members to obtain their input and to assure that all crew members understand the assignment and their responsibilities. Crew members will be reminded that if hazardous situations arise or work conditions change substantially, they are encouraged to call a halt to the work and look out for other crew members. If that occurs, a new Form 1812 must be prepared.
Nearly all of our field assignments require several days for completion. Form 1812 will be reviewed at the start of each day for that day's briefing on the work to be done.
Each crew member will have communication equipment and the phone numbers to be called in the event of an emergency.
Lindsey WolfeDivision Manager
Daily, crew supervisors are to review the job plan with crew members, seeking their input, and whenever the scope of the job changes.
Beta Company Assigned ...