74 Operations Management
Two conventions exist in
constructing a network:
representing the activity
on arc (AOA) and
representing the activity
on node (AON).
(c) Develop the detailed design
(d) Create marketing infrastructure
(e) Plan production
(f) Reach the market
Each of these can be considered as an activity. It is easy to recognize that
each of these activities consumes some resources and time for comple-
tion. There are also some constraints in the order in which the activities
could be performed. For example, without understanding the market
needs, it is not possible to develop the conceptual design. Likewise,
without the conceptual design, ...