Design of Manufacturing Processes 243
We assign tasks to the five workstations on the
basis of the following two criteria:
8
(i) The workstation times should not exceed the
maximum permissible cycle time of 90 seconds
(ii) The precedence relationships among the tasks
need to be honoured
The average utilization of the resources can be com-
puted as follows (Eq. 9.4):
Average utilization
Sum of all task times
No. of workstatio
=
nns Cycle time
×
Average utilization
Sum of all task times
No. of workstatio
=
nns Cycle time
380
590
84.4%
=
×
=
(e) Design of assembly shop with six workstations
(Table 9.10 presents the details):
We assign tasks to the six ...