84 Operations Management
all activities to get the direct cost for the project when
there is no crashing. The direct costs for the project is
`108,000. Therefore, the total cost of the project with
no crashing is `283,000.
Cost Per Week of Crashing the Activities
From the data in Table 4.7, we see that three activities
cannot be crashed. Therefore, our focus is only on the
remaining activity. We first compute the cost of crashing
per week using the data in Table 4.7 and Eq. 4.1. Let us
consider Activity A. The normal cost is `12,000 and the
crash cost is `20,000. Since the activity could be crashed
by two weeks, the cost per week of crashing is ...