94 Operations Management
9. Consider Problem 6. If the manpower requirements for
the activities have been estimated as per the data given
in Table 4.21.
TABLE 4.21 Data for Problem 9
Activity Manpower Required
A 80
B 30
C 30
D 40
E 30
F 40
G 80
(a) Prepare a manpower loading chart on the basis of
early start schedules for the project.
(b) Are you satisfied with the loading pattern? If not, devise
an alternative schedule for the manpower loading.
(c) The organization maintains a constant workforce of
70 workers and hires and lays off workers depending
on the requirement on a week-by-week basis. If
the hiring charges are `2,500 per worker hired and