414 ◾ The Security Risk Assessment Handbook
© 2011 by Taylor & Francis Group, LLC
Table12.3 Hours Allocation Example
Phase/Task Resource 1 Resource 2 Resource 3
Pre-on-site:
Project planning 6 2
Document review 8
Interview preparation 2
On-site assessment:
Document follow-up 3
Interviews 3
Inspection 2
Observations 2
Testing 16
Results analysis:
Data analysis 8 8 2
Create risk statements 6 6
Team review 6 6 6
Additional research 8 8
Reporting:
Document specification 2
Annotated outline 4
Draft 8 20
Final 2 6 2
Briefing 4 2
Task total: 158 hours 64 82 12
Management: 17 hours
Net: 175 hours
Note: The project manager should sketch out the allocation of the hours to the ...