This appendix provides a complete WBS to support the graphic representation in Chapter 7.
The complete WBS dictionary that accompanies the WBS and describes the contents of each WBS element is available at http://fast.faa.gov/wbs/wbssec.htm.
1 MISSION ANALYSIS
1.1 Identify Projected Demand for Services
1.2 Identify Technological Opportunities
1.3 Identify Projected Supply of Services
1.4 Mission Needs Analysis and Assessment
1.5 Initial Requirements Definition
2 INVESTMENT ANALYSIS
2.1 Initial Investment Decision
2.1.1 Planning
2.1.2 Analysis
2.1.3 Documentation
2.2 Final Investment Decision
2.2.1 Planning
2.2.2 Analysis
2.2.3 Documentation
2.3 Rebaseline Decision
3 SOLUTION DEVELOPMENT
3.1 Program ...