| Key processes: | Commissioning servicesCommissioning documentationQuality management and control |
| Key objective: | ‘Is it performing as designed?’ |
| Key deliverables: | Commissioning documentation |
| Key resources: | Client teamProject managerDesign teamCDM coordinatorConstructor teamCommissioning team |
Part of the construction stage, this stage confirms that the building services systems have been installed in compliance with the design, have been fully tested and have been proven to be fully functional.
Outcomes:
It must be stressed that the sequencing of this stage does not mean that the activities involved only take place at the end of the construction stage. Commissioning is a very important part of the construction process and must be addressed and considered very early on within the project. The following are suggested activities that must be considered well before this stage: