Project Integration Management ◾ 31
quality, procurement, communications, and human resources
(staffmanagement and staff development) processes. In addi-
tion to management plans for each knowledge area, project
plans typically include specic scope, time, cost, and risk
information at an appropriate level of detail.
For example, the project management plans include the
project charter, scope statement, and WBS (possibly down to
Level 3). The plan also includes cost estimates and schedule
information at the level needed for visibility and control. The
plan includes the cost and schedule baseline and identies key
resource requirements from the staff management plan. It also
identies risks and planned mitigation strategies as appropriate,