48 ◾ Project Management Maturity Model
Development of a technical requirement document is part of
the project management process if needed.
Scope Validation
A process exists for validating project deliverables. All large or
high-value projects require validation of scope. Management
reviews project deliverables. The project manager (or team)
always veries project scope (what is to be included in or
excluded from the project) with the client or customer.
Scope Change Control
Standard templates exist to monitor project status and manage
scope baseline. All large or high-value projects require moni-
toring of project status and management of scope baselines.
A dened and documented scope change control process
is in place, but not all of the proje ...