RFID Project Management 143
11.8 DEVELOPING THE PROJECT PLAN
The project planning process as a minimum consists of developing a WBS, an LRC, and a Gantt
chart.
11.8.1 woRk BReAkdown stRuctuRe
A WBS is a successively lower division of project tasks into subtasks. On the rst or top-most level,
the WBS might consist of only a few of the steps outlined in this book. How many lower levels
to use in the project plan is at the discretion of the project manager. However, for the WBS to be
meaningful, it is likely to require at least two levels. The following table illustrates a basic two-level
WBS for an RFID project.
WBS Activity
1.0 Problem formulation ...