EPC Contractor to begin work earlier than Financial Close, and therefore
provide the EPC Contractor with temporary guarantees against which the
work can progress until Financial Close has been reached— cf. §7.1.2.)
The EPC Contractor should also ensure that the EPC Contract payment
schedule is linked as closely as possible to its own financial exposure to di-
rect costs and payments to subcontractors and equipment suppliers, so that
if the Project Company does collapse the EPC Contractor’s losses can be
limited.
§8.5.4 C
ONSTRUCTION
C
OST
O
VERRUNS
The effects of an overrun in construction costs against the budget on which the
funding structure has been based are:
• There may be insufficient funding available to complete the project, thus
forcing the Sponsors ...