TABLE 7 SHOWS how different levels of complexity may affect project management processes according to the major PMBoK knowledge areas.
TABLE 7
Project complexity and PMBoK knowledge areas
| LEVEL OF PROJECT COMPLEXITY | |||
| knowledge area | Assembly | System | Array |
| Integration | Simple integration; quick transfer to operations and sales | Extensive integration period to make sure the entire system is functioning as planned; cross-functional and customer involvement; gradual integration of subsystems; extensive testing during system integration | Integration of subsystems by subcontractors; rare cases of full-scale integration by main contractor |
| Scope | Allow only changes that ... | ||