Switching Tasks to Auto Scheduled Mode

So far, the work tasks in your project (but not the summary tasks) have been set to Manually Scheduled mode. If you want Project to calculate your schedule for you (see Automatically Scheduling Tasks), you need to switch some or all of your tasks to Auto Scheduled mode. That way, Project can take care of recalculating start dates, finish dates, and durations as you add more details to your plan.

Here’s how to change the tasks in the sample project to Auto Scheduled mode:

  1. Click the Task Mode cell for the first summary task (which is already set to Auto Scheduled mode).

    A down arrow appears, which you can click if you want to choose either Manually Scheduled or Auto Scheduled from a drop-down menu. In addition, a fill handle (a green square), appears at the bottom right of the cell.

  2. Position your cursor over the fill handle. When it changes to a + sign, drag over the Task Mode cells of all the tasks in the list.

    The icons in the Task Mode cells change to indicate that the tasks are Auto Scheduled.

Become an O’Reilly member and get unlimited access to this title plus top books and audiobooks from O’Reilly and nearly 200 top publishers, thousands of courses curated by job role, 150+ live events each month,
and much more.

Read now

Unlock full access

More than 5,000 organizations count on O’Reilly

AirBnbBlueOriginElectronic ArtsHomeDepotNasdaqRakutenTata Consultancy Services

QuotationMarkO’Reilly covers everything we've got, with content to help us build a world-class technology community, upgrade the capabilities and competencies of our teams, and improve overall team performance as well as their engagement.
Julian F.
Head of Cybersecurity
QuotationMarkI wanted to learn C and C++, but it didn't click for me until I picked up an O'Reilly book. When I went on the O’Reilly platform, I was astonished to find all the books there, plus live events and sandboxes so you could play around with the technology.
Addison B.
Field Engineer
QuotationMarkI’ve been on the O’Reilly platform for more than eight years. I use a couple of learning platforms, but I'm on O'Reilly more than anybody else. When you're there, you start learning. I'm never disappointed.
Amir M.
Data Platform Tech Lead
QuotationMarkI'm always learning. So when I got on to O'Reilly, I was like a kid in a candy store. There are playlists. There are answers. There's on-demand training. It's worth its weight in gold, in terms of what it allows me to do.
Mark W.
Embedded Software Engineer

You might also like

Microsoft Project 2013: Step by Step

Microsoft Project 2013: Step by Step

Carl Chatfield, Timothy Johnson

Publisher Resources

ISBN: 9781449357955Errata Page