Linking Tasks

Task dependencies (a.k.a. task links or task relationships) are what transform a ragtag group of tasks into a well-mannered project schedule, so Project offers several ways to create and modify all types of task dependencies. This section describes your options and the pros and cons of each one, and then walks you through several methods for creating task dependencies, starting with the most common type—finish-to-start.

How Tasks Affect One Another

Clearly defined task dependencies are essential to creating an easy-to-maintain schedule. Like a baton passed from one relay runner to the next, the start or finish date of one task (the predecessor) determines when the second task (the successor) starts or finishes. (That doesn’t necessarily mean the predecessor task starts before the successor—the predecessor task is just the one that triggers the start or finish of the successor.)

When you get your task dependencies in place (and use Project’s automatic scheduling), project tasks snuggle cozily into sequence, and the program can automatically calculate task start and finish dates—and from those, the end date of the entire project.

As Figure 7-5 illustrates, Project indicates task dependencies with small arrows showing how the start or end point of each task relates to the start or end of another.

Although the tasks in a relationship are called successor and predecessor, a dependency isn’t about which task starts first—it’s about which task controls the timing of the other. For example, in a start-to-start dependency, both tasks start at the same time, but the start of the predecessor task controls when the successor task starts.

Figure 7-5. Although the tasks in a relationship are called successor and predecessor, ...

Become an O’Reilly member and get unlimited access to this title plus top books and audiobooks from O’Reilly and nearly 200 top publishers, thousands of courses curated by job role, 150+ live events each month,
and much more.

Read now

Unlock full access

More than 5,000 organizations count on O’Reilly

AirBnbBlueOriginElectronic ArtsHomeDepotNasdaqRakutenTata Consultancy Services

QuotationMarkO’Reilly covers everything we've got, with content to help us build a world-class technology community, upgrade the capabilities and competencies of our teams, and improve overall team performance as well as their engagement.
Julian F.
Head of Cybersecurity
QuotationMarkI wanted to learn C and C++, but it didn't click for me until I picked up an O'Reilly book. When I went on the O’Reilly platform, I was astonished to find all the books there, plus live events and sandboxes so you could play around with the technology.
Addison B.
Field Engineer
QuotationMarkI’ve been on the O’Reilly platform for more than eight years. I use a couple of learning platforms, but I'm on O'Reilly more than anybody else. When you're there, you start learning. I'm never disappointed.
Amir M.
Data Platform Tech Lead
QuotationMarkI'm always learning. So when I got on to O'Reilly, I was like a kid in a candy store. There are playlists. There are answers. There's on-demand training. It's worth its weight in gold, in terms of what it allows me to do.
Mark W.
Embedded Software Engineer

You might also like

Microsoft Project 2013: Step by Step

Microsoft Project 2013: Step by Step

Carl Chatfield, Timothy Johnson

Publisher Resources

ISBN: 9781449357955Errata Page