Statusing refers to the practice of applying actual dates, costs, and hours to the project. This is when your planned schedule begins to reflect what actually happened on the project. This can mean simply updating actual start and/or finish dates and remaining durations for activities, or updating hours worked and remaining hours for resources, or updating completed activity percentage. But often the situation is more complicated than that and a number of questions must be considered:
The answers to these questions will vary widely between companies, ...