1. In a PERT analysis, what is the probability that an activity will be completed no later than the PERT estimate?

(a) 50.00%

(b) 84.13%

(c) 15.87%

(d) 61.79%

2. The triple constraints include:

(a) risk, quality, and procurement.

(b) time, risk, and quality.

(c) time, cost, and quality.

(d) time, cost, and performance.

3. A critical path activity can be compressed from eight ...