40 • Managing Supply Chain Risk
TABLE2.14 (Continued)
FG “Scorecard”
Supplier List Severity/Impact
Supplier Product SCL Product Spending Tooling Cost
Product
Criticality Recovery Time
Contingency
Sources
15% weight 10% weight 30% Weight 30% Weight
15% Weight
Overall
impact
1 Very low 0–100k 1 Very low No tooling 1 Very low 1 Very Low 1 to 4
wks recovery
1 Very low—o the
shelf
2 Low 100k– 250k 2 Low Transferable/
Under 10k
2 Low 2 Low 4 to 8 wks 2 Low—multiple
sources
3 Medium 250k–500k 3 Medium 10k–25k 3 Medium 3 Medium 9 to
12 wks
3 Medium—2–5
available suppliers
4 High 500k–1 MM 4 High 25k–50k 4 High 4 High 3 to 6
months
4 High—1–2
suppliers
5 Very high ...