166 • Managing Supply Chain Risk
TABLE7.6
Steelcase Supply Process PFMEA
Supply Process Failure Mode Effects Analysis
Review team: Process
stakeholders:
Date
Tollgate 1 completed:
Supplier: Key project
dates:
Tollgate 2 completed:
Product: Tollgate 3 completed:
Item and Function
Potential Failure
Mode
Eects of Failure
Projected Severity at
1st ship Rank 1–10
Cause(s) or
Mechanism(s)
of Failure
Projected Probability
of Occurrence at
1st ship Rank 1–10
Key Process or
Product
Characteristic Yes/ No
Current Design
Controls
Projected Probability
of Detection at
1st ship Rank 1–10
Ranking or Priority
Number
(Calculated 4×6×9)
Proposed Action(s)
Responsibility a