APPENDIX B
Discussion Responses and Exercise Solutions
CHAPTER 3Exercise Solutions
TV = $289,000 = ($40,000 + $30,000 + $28,000 + $17,000 + $22,000 + $24,000 + $38,000 + $90,000)
PV = $178,540 = ($40,000 + $30,000 + $28,000 + $17,000 + $21,120 + $23,040 + $19,380)
AC = $137,500
EV = $129,800 = ($40,000 + $30,000 + $28,000 + $17,000 + $11,000 +$0 + $3,800)
CV = ($7,700) unfavorable = ($129,800 – $137,500) CPI = .944; project over budget = ($129,800 / $137,500)
SV = ($48,740) unfavorable = ($129,800 – $178,540); SPI =.727; project behind schedule = ($129,800 / $178,540)
“Optimistic” EAC = $306,144 = ($137,500 + $168,644). “Pessimistic” EAC = ...
Get A Practical Guide to Earned Value Project Management, 2nd Edition now with the O’Reilly learning platform.
O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.