EVMS has been in practice for a number of years and has had only minor changes since it was originally developed. We are now beginning to see several emerging practices that could become mainstream in a short time.
One of these emerging practices is performance-based earned value, or PBEV (Solomon and Young 2007). Solomon and Young’s major contributions are (1) the insertion of product technical requirements and expected quality into a project’s plan;1 (2) recognizing EV for partially achieving product requirements, such as quality; and (3) formally integrating risk management tasks, such as estimated rework, into the EV system. They provide many examples and alternative methods of ...