274 Power System Transients
suppressing short-term sheath overvoltage, as bonding leads to SVLs can be
much shorter than when using the link box.
3.4 Studies on Recent and Planned EHV AC Cable Projects
This section introduces recent and planned EHV AC cable projects and cable
system transients studied for the projects. In order to compensate for the
large charging capacity of EHV AC cables, shunt reactors are often installed
together with these cables. The large charging capacity and large shunt reac-
tors lower the natural frequency of the network which, at times, make it
necessary to conduct resonance overvoltage studies. Load-shedding over