Dress rehearsal (cutover)

  • Purpose: The main purpose of this deliverable is to mock up the cutover procedure by executing an end to end solution. It should include everything that is planned to go-live, even a late bug fix or a correction that was done last minute.
  • Approach: On-premise.
  • Deliverable(s): Dress rehearsal.
  • Tasks summary:
    • Test plan created in realization phase is reviewed and updated if required
    • Prepare and execute the planned and scheduled test (which are supposed to run in production as well)
    • Get a final sign-off by sharing the findings and recommendations from the technical system test performed previously