KEY LEARNING
• Service orchestration should be requested from the vendor.
• Integration of the new AS with the core platform is a
very complex project and requires a significant amount
of time for implementation.
• Additional licenses are needed for core nodes.
• Synchronized and on-time provisioning should be provided.
• Mediation logic (event charging information from AS
and core nodes).
4.2 NT Rollout
e NT rollout has two elements:
I. Network and technical product readiness
• Planning the adjustments of the network elements.
II. Internal resources preparation and planning
• Planning the actual migrat ...