187
go to market
be planned to secure availability of resources on time and in expected
quality. erefore, resource planning needs to be strongly linked to
overall migration strategy, meaning the migration plan (e.g., product
and area sequencing) and the underlying assumptions on application
of different migration types (e.g., automigration, supported migra-
tion, 2-in-1 migration).
Assumptions on resource needs and actual demand should be con-
stantly tracked and monitored during migration to ensure the quality
of the process (customer perception and response rate in case of faults)
and achievement of migration targets. In the next section, the app ...