PROJECT PACE AND TRADITIONALPROJECT MANAGEMENT
TABLE 8 DESCRIBES how various levels of project pace affect project management according to the major PMBoK knowledge areas. As you can see, with increased pace, management attention is increasingly focused on reducing the risk of project delays.
TABLE 8
Project pace and the PMBoK knowledge areas
| PMBoK knowledge area | LEVEL OF PROJECT PACE | |||
| Regular | Fast/Competitive | Time-Critical | Blitz | |
| Integration | Gradual integration until final system is completed and tested | Intensive integration and testing to ensure timely entry to the market | Carefully planned periods of integration to ensure product preparedness on time | No time for integration in blitz projects |
| Scope | Use of regular ... | |||