The Planning Phase of an Incremental SDPM Strategy for the Staged Delivery Waterfall Model
Figure 12-4 is the Planning Phase of the Incremental SDPM strategy for the Staged Delivery Waterfall model.
Figure 12-4. Planning Phase of an Incremental SDPM strategy for the Staged Delivery Waterfall model
For planning the Incremental SDPM strategy for the Staged Delivery Waterfall model, you would know all of the planning input. The RBS would have been generated during the Scoping Phase and is all of the input needed to build a complete project plan. There are six major tasks that you need to do to generate the project plan. They are:
Building the complete WBS
Estimating task duration
Estimating resource requirements
Building the precedence diagram
Allocating functions and features to determine number of stages
Creating the initial project schedule
Each of these tasks is briefly described in the following subsections.
Building the Complete WBS
The RBS is the only input needed here. The RBS is a deliverables-based WBS and needs only to be further decomposed to the task level. Each feature is therefore decomposed until it satisfies the completion criteria. See Appendix E for details.
Estimating Task Duration
Features are rather primitive deliverables and the clock time needed to build them should be easy to estimate. Features are likely to have been defined for other projects. If they are ...
Get Effective Software Project Management now with the O’Reilly learning platform.
O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.