Estimating Aggregate Cost

As Figure 10.7 shows, each Task holds a collection of EstimationLogEntry instances. These logs model the specific occasions when a team member enters a new estimate of hours remaining. In practical terms, how many Task elements will each BacklogItem hold, and how many EstimationLogEntry elements will a given Task hold? It’s hard to say exactly. It’s largely a measure of how complex any one task is and how long a sprint lasts. But some back-of-the-envelope (BOTE) calculations might help [Bentley].

Task hours are usually reestimated each day after a team member works on a given task. Let’s say that most sprints are either two or three weeks in length. There will be longer sprints, but a two- to three-week time span is ...

With Safari, you learn the way you learn best. Get unlimited access to videos, live online training, learning paths, books, interactive tutorials, and more.

Start Free Trial

No credit card required