SPECIFICATION AND DRAWINGS
Local bye-laws and regulations
29
7. The Contractor shall ascertain and act in accordance with
any local bye-laws and regulations which may affect the work
under this Contract. Any cost for the stamping of valves,
fittings and the like must be covered by the Contractor in his
tender.
Reception and storage of materials
8. The Contractor shall provide proper storage for all
materials, tubes, fittings, etc. delivered to the site, which
must be received at the site by the Contractor. Tubes and
fittings stored on the ground outside will not be approved for
use.
The Contractor will be fully responsible for reception an