128 ESTIMATING LABOUR REQUIRED FOR ERECTION
Total estimated time 19*5
Section 2
LIGHT GAUGE COPPER PIPE AND FITTINGS
(B.S.2871:
Part 1)
Off load pipe, sockets, and brackets at site, and move to fixing position on ground
floor of new building. Arrange pipe run from plan, level and mark out for brackets,
cut pipe to required length and fit sockets (soldered or compression joints). Fix pipe-
work to brackets at low level on wall, and clean
up
joints.
Off load fittings and valves
at site and move to fixing position. Measure up for fixing, cut pipe and fit compression
or soldered capillary fitting into the line and clean up joints.
Nominal pipe size ...