146 ESTIMATING LABOUR REQUIRED FOR ERECTION
Section 24
MISCELLANEOUS ITEMS OF FIXING
Off load, move to fixing position, and fix the following
:
Hours,
Job
fitter and
mate
Tool rack on boiler room wall
1-5
Starter, switch, time control, control box,
1-5
draught gauge
Room thermostat 10
Outdoor thermostat
30
Duct thermostat 20
Capillary tubing per metre run
0-25
Small bore tubing for gauges, etc. per metre 015
run
Draught regulator or stabiliser, fix and set
20
Radiator wall shield
20
Towel rail to wall
40
Towel rail to floor
20
H.W.S. mixing valve to wall
1-5
H.W.S. shower rose or spray fitting to wall
1-5
Hit and miss ventilator in wal