PREPARING THE TENDER 171
SUMMARY OF TENDER
SUB-CONTRACT FOR CHURCH HALL HEATING
£
Ρ
(1) Total cost of materials
538
41
(2) Cost of labour, 196 hours at £1.00
196
00
(3) National Health, Redundancy Fund, Holiday Credits, Sickness
and Accident Insurance 22 35
(4) Travelling allowance
18
00
(5) Selective Employment Tax 11 76
(6) Add 15 per cent on items 2, 3, 4 and 5 to allow for sub-contract
conditions 37 22
(7) Cartage of materials. 4 journeys at 3 hours per journey. 12 hours
at £1.40 per hour 16 80
(8) Insulating pipes in boiler room
29 65
(9) Wear and tear of tools. 3 per cent of net labour cost 5 88
876 07
(10) Overheads and profi ...