154 ESTIMATING LABOUR REQUIRED FOR ERECTION
Section 36
FORCED WARM AIR DOMESTIC CENTRAL HEATING
Light Gauge Ductwork
Off load at site, and move ladders, scaffolding, ducts, fittings, brackets, insulating
materials and tools, to fixing position on the ground floor of a new unoccupied
building. Mark out duct runs and fixings. Fix hangers and brackets. Trim ductwork,
joint and erect straight runs. Mark out for, trim and fix branches, bends, etc.
Remove ladders or scaffolding, and clean up.
A. Diameter of duct or length of longest side (approx.).
B.
Straight runs per metre.
C.
Fit bend, branch, damper, starting elbow, starting collar, transitio ...