Calculate the fully loaded cost of labor for the project team using the following data. What are the costs for the individual project team members? What is the fully loaded cost of labor?
Name |
Hours Needed |
Overhead Charge |
Personal Time Rate |
Hourly Rate |
Fully Loaded Labor Cost |
|---|---|---|---|---|---|
John |
40 |
1.80 |
1.12 |
$21/hr |
|
Bill |
40 |
1.80 |
1.12 |
$40/hr |
|
J.P. |
60 |
1.35 |
1.05 |
$10/hr |
|
Sonny |
25 |
1.80 |
1.12 |
$32/hr |
|
|
|||||
We use the formula for calculating fully loaded costs, given as:
Applying each rate given above in turn, we fill in the fully loaded cost table ...