Develop an in-depth cost estimate to support your initial project proposal narrative and scope statement, including the Work Breakdown Structure. Create a detailed justification of personnel costs, materials costs, overhead, and other forms of costs that are likely to accrue to your project. Be specific, particularly about personnel costs and commitment of time. For example, your cost table could look something like the following:
Personnel |
Level |
Rate |
Loaded Rate |
Labor-Weeks Needed* |
Total Cost |
|---|---|---|---|---|---|
Programmer |
Senior |
$35 |
$49/hr |
20 |
$39,200 |
Sys. Analyst |
Junior |
$22 |
$31/hr |
10 |
$12,400 |
*40-hour work week |
|||||
Remember that the “loaded rate” assumes that you include the organization’s overhead ...