Exercise 12.23

Refer to the following activity network table. Enter this information using MS Project to produce a Gantt chart. Assume that each resource has been assigned to the project activity on a full-time (8 hours/day or 40 hours/week) basis.

Activity

Duration

Predecessors

Resource Assigned

A. User survey

4

None

Gail Wilkins

B. Coding

12

A

Tom Hodges

C. Debug

5

B

Wilson Pitts

D. Design interface

6

A, C

Sue Ryan

E. Develop training

5

D

Reed Taylor

Exercise 12.24

Using the information from Exercise 12.23, produce a resource usage sheet that identifies the total number of hours and daily commitments of each project team member.

Exercise 12.25

Refer to the activity network table shown in Exercise