Refer to the following activity network table. Enter this information using MS Project to produce a Gantt chart. Assume that each resource has been assigned to the project activity on a full-time (8 hours/day or 40 hours/week) basis.
Activity |
Duration |
Predecessors |
Resource Assigned |
|---|---|---|---|
A. User survey |
4 |
None |
Gail Wilkins |
B. Coding |
12 |
A |
Tom Hodges |
C. Debug |
5 |
B |
Wilson Pitts |
D. Design interface |
6 |
A, C |
Sue Ryan |
E. Develop training |
5 |
D |
Reed Taylor |
Using the information from Exercise 12.23, produce a resource usage sheet that identifies the total number of hours and daily commitments of each project team member.
Refer to the activity network table shown in Exercise