APPENDIX B Tutorial for MS Project 2016
Exercise A: Constructing the Network: Site Preparation Project
Task |
Title |
Predecessors |
Duration |
---|---|---|---|
A |
Contract Approval |
— |
5 |
B |
Site Survey |
A |
5 |
C |
Permit Application |
A |
4 |
D |
Grading |
B, C |
5 |
E |
Sewer Lines |
B |
7 |
F |
Base Paving |
D |
3 |
G |
City Approval |
C, F |
6 |
H |
Final Paving |
E, G |
8 |
Using the previous information, complete the following tasks:
Construct this network using MS Project 2016.
Identify the critical path. How long will this project take?
Assign and level resources.
Suppose Rose is responsible for Activities B and C. Are there any resource conflicts? How do we know?
Show the same project with a Gantt chart and a network diagram.
1. CONSTRUCT THIS NETWORK USING MS PROJECT 2016
To create an MS Project ...