Assume the following information:
Activity |
Predecessors |
|---|---|
A |
— |
B |
A |
C |
B |
D |
B |
E |
C, D |
F |
C |
G |
E, F |
H |
D, G |
Create an activity network that shows the sequential logic between the project tasks. Can you identify merge activities? Burst activities?
This activity network can be solved as shown in Figure 9.26. The merge points in the network are activities E, G, and H. The burst activities are activities B, C, and D.

Assume that you have the following pessimistic, likely, and optimistic estimates ...