January 2018
Intermediate to advanced
480 pages
33h 56m
English
13.38. b—SPI is calculated by dividing earned value (EV) by planned value (PV).
13.39. b—Earned Value is $1,075 to date.
13.40. c—CPI is calculated as earned value (EV) divided by actual cost (AC). In this case, that is $1.075/$1,290, or 0.83.
13.41. b—Estimate to complete.
13.42. d—Estimate to completion is based on the formula or $1,375.
13.43. a—The most serious information from this meeting is the significant schedule delay and this should be reported to top management.
13.44. d—With a planned finish of 12 weeks and an SPI of .75, expected completion is 12/.75, or 16 weeks.
13.45. b—This is good news. You are earning value on the project at a rate of 1.4 times the rate you had planned (PV).
13.46. c—Schedule ...
Read now
Unlock full access